A construction draw schedule template for home builders

A draw schedule splits a construction loan into payments the lender releases as the work gets done. Here is how one usually works, and a sample for a custom home you can start from. Your lender sets the real stages, so check them against your loan agreement.

  • A sample six-draw schedule for a custom home
  • What happens between a draw request and the money
  • How retainage works
  • What to send with each draw request
Create a free account

Free during the beta. No credit card.

How a draw schedule works

The loan is split into draws, and each draw is tied to a stage of the work. When a stage is done, you send the lender a draw request. The lender usually sends an inspector to check the work, then releases the money, often less a share held back as retainage.

A sample draw schedule for a custom home

The shares are a sample. Lenders set their own stages, and some fund the lot and fees separately.

  • 1. Foundation

    Due when:
    Footings, walls and backfill are done
    Share of the loan:
    15%
  • 2. Framing

    Due when:
    The house is framed and sheathed
    Share of the loan:
    20%
  • 3. Dry-in

    Due when:
    Roof on, windows and exterior doors in
    Share of the loan:
    15%
  • 4. Rough-ins

    Due when:
    Plumbing, electrical and HVAC rough-in passed inspection
    Share of the loan:
    15%
  • 5. Drywall and trim

    Due when:
    Drywall finished, cabinets and trim in
    Share of the loan:
    20%
  • 6. Final

    Due when:
    Final inspection passed and the house is complete
    Share of the loan:
    15%

Retainage

Many lenders and owners hold back part of each draw, often 5 to 10 percent, until the house is finished. Keep a running total of what's held so the last draw isn't a surprise, and know what you owe your subs out of it.

What to send with a draw request

A complete request gets paid faster. Most lenders want:

  • The stage it covers and the line items in it
  • What was drawn before and what this draw asks for
  • Progress photos from the job site
  • Lien waivers from the subs paid from the last draw

Run your draw schedule in HomeTakeOff

Set up the draws once, tied to the phases of your schedule. Each draw tracks its line items, retainage and photos, can track lien waivers from your subs, and turns into a draw request you can print or save as a PDF.

HomeTakeOff draw schedule for a construction loan with funded, submitted and draft draws and retainage held

Questions builders ask

How many draws does a construction loan have?

Often five to seven for a new home, but the lender decides. The sample here has six.

What is retainage on a construction loan?

A share of each draw, often 5 to 10 percent, that the lender or owner holds back until the work is finished.

Who checks the work before a draw is paid?

Usually an inspector the lender sends to the job site. Progress photos with the request help it go quickly.